Pre commissioning and commissioning: Why your project probably isn't ready yet

Pre commissioning and commissioning: Why your project probably isn't ready yet

You've seen it happen. A multi-million dollar plant sits idle while engineers scramble around with clipboards and laptops, looking stressed. The ribbon-cutting ceremony was supposed to be last week. Now, everyone is arguing about why the pumps won't start or why the control system is throwing "ghost" alarms at 3:00 AM. This is the reality when pre commissioning and commissioning are treated as an afterthought rather than the actual backbone of the project.

It’s messy. It’s loud. Honestly, it’s where the "paper" engineering meets the cold, hard reality of physics.

Most people think you just flip a switch once the pipes are welded. You don't. If you do, things tend to explode, or at the very least, break expensive seals. We're talking about a rigorous, often tedious transition from a "construction site" to a "living asset." It's the difference between a car that looks nice in the driveway and one that actually makes it to 100 mph without the wheels falling off.

The messy line between building and breathing

Construction is about "static" completion. You bolted the flange. You ran the cable. You painted the tank. That's great, but it doesn't mean the system works. Pre commissioning is the bridge. It’s the phase where we start poking the beast to see if it’s awake.

Think of it as the "dry" phase. We aren't introducing the spicy stuff yet—no high-pressure steam, no volatile chemicals, no raw sewage. We are checking the nervous system. Is the wiring correct? Did the contractor leave a sandwich inside the ducting? It happens more often than you'd think. I once saw a heavy-duty turbine fail because a stray rag was left in the intake during "clean" construction.

🔗 Read more: nvda stock prediction 2025: Why Most People Got the AI Bubble Wrong

During pre commissioning, the focus is on Cold Commissioning activities. We do hydrostatic testing. We flush the lines. We perform "loop checks" to ensure that when an operator clicks "Open" on a screen in the control room, the actual valve in the field moves. If it doesn't move, or if the wrong one moves, you’ve got a problem. This is where you find out the drawings were wrong. It's better to find that out now than when the system is full of 400-degree oil.

What actually happens in the field?

It isn't just checking boxes. It’s a hunt for errors.

  1. Cleaning and Flushing: You’d be amazed at the amount of construction debris—welding slag, dirt, pebbles—that lives inside "new" piping. We blow air or pump water through at high velocities to get it out. If you skip this, that slag ends up in your $200,000 pump.
  2. Pressure Testing: We fill systems with water or nitrogen to 1.5 times the design pressure. We wait. We watch the gauges. If the needle drops, there’s a leak. Find it now, or regret it later.
  3. Loop Testing: This is the big one. There are thousands of instruments in a modern refinery or power plant. Every single one needs to be verified. Does the 4-20mA signal actually correspond to the right pressure reading?

Moving into the "Hot" zone: Actual Commissioning

Once the pre-work is done, you move into commissioning proper. This is "Hot Commissioning." This is when the heartbeat starts. We introduce the actual process fluids. We bring the heat up. We ramp up the pressure.

It’s a high-stakes game of "What if?"

You have to test the safety logic. We call this Cause and Effect testing. If the pressure in Tank A hits a certain limit, does the emergency shutdown valve (ESD) actually slam shut in under two seconds? It has to. Not 90% of the time. Every time. Organizations like the International Society of Automation (ISA) have entire standards, like ISA-84, just to manage these safetyed instrumented systems. If you aren't following them, you aren't really commissioning; you're just gambling with people's lives.

The "S" Curve and the reality of delays

Every project manager has a beautiful spreadsheet showing a perfect "S" curve for commissioning. It never looks like that in real life. Real life looks like a jagged EKG. You hit a snag with a proprietary software driver. A seal fails on a compressor. A shipment of specialized catalyst is delayed at a port in Singapore.

Commissioning is where the schedule goes to die if you haven't planned for "known unknowns."

Most experts, including those from the Association for the Advancement of Cost Engineering (AACE), suggest that commissioning should account for roughly 5% to 15% of the total project budget. If your budget says 2%, you’re already in trouble. You just don't know it yet. You’ll spend that money anyway, but it’ll be in "emergency" rates and overnight shipping fees instead of planned labor.

Why things go sideways (The human element)

We talk about valves and code, but commissioning is mostly about people. It’s about the handoff. The construction crew wants to go home. They are tired. They want to sign off and move to the next job. The operations team—the people who actually have to run the plant for the next 20 years—are terrified. They see a complex machine they don't quite trust yet.

There is a natural tension here.

Construction says, "It's built to the drawing."
Operations says, "I don't care about the drawing; it's vibrating weirdly."

The Commissioning Manager is the referee. This person needs to be a bit of a diplomat and a bit of a drill sergeant. They have to manage the Mechanical Completion certificates. This is the legal "handshake." Once that paper is signed, the responsibility shifts. It’s a massive liability transfer. If you sign it too early because you're chasing a bonus, you might be inheriting a nightmare.

Systems Thinking vs. Component Thinking

The biggest mistake is thinking in components. "The pump works." "The motor works." Great. But does the system work?

Take a HVAC system in a data center. The chillers might pass their individual tests. The fans might spin. But when you put them together, do they fight each other? Does the control logic cause the chillers to "short cycle," killing the compressors in six months? Commissioning is about the harmony of the components. It's the rehearsal before the concert. You don't want to find out the violinist and the cellist are playing in different keys on opening night.

The Digital Twin and modern Commissioning

In 2026, we aren't just using clipboards. We use digital twins.

Companies like Bentley Systems or Siemens provide software where the physical sensor in the field updates a 3D model in real-time. During commissioning, we can compare the "as-built" data with the "as-designed" model instantly. If a temperature sensor is reading 10 degrees off what the simulation predicted, we know something is wrong with the flow or the insulation before we even see the smoke.

However, don't let the tech fool you.

👉 See also: USD to Kenya Shillings Exchange Rate Today: What Most People Get Wrong

A digital twin is only as good as the data fed into it. If the guy in the field "ghost-writes" a check-sheet (marking things as done without actually checking them), the digital twin is just a digital lie. Verification is everything. "Trust, but verify" is the mantra of any commissioning lead worth their salt.

Real-world fallout: When it goes wrong

Remember the Deepwater Horizon? While that was a complex drilling disaster, a significant portion of the post-event analysis focused on the failure of testing and the misinterpretation of pressure tests. That is commissioning at its most critical. If the test says something is wrong, believe the test. Don't "rationalize" away a bad reading because you are behind schedule.

In the commercial world, look at the Berlin Brandenburg Airport. It opened nearly a decade late. Why? Primarily because the fire safety and smoke extraction systems failed their commissioning phases repeatedly. The systems were so complex and poorly integrated that they simply couldn't be proven safe. They had to rip out and redo massive sections of the infrastructure.

Practical Steps for a Successful Startup

If you are overseeing a project right now, here is the "no-nonsense" checklist to keep your head above water.

Involve Operations early.
Don't wait until the day of commissioning to show the operators the plant. Get them involved during the late stages of construction. Let them walk the lines. They will find the "un-maintainable" valve that the designer put 12 feet in the air with no ladder access. Fixing it now costs $500. Fixing it later costs $50,000 in downtime.

Cleanliness is next to godliness.
I cannot stress this enough. Most mechanical failures during startup are caused by "foreign material exclusion" issues. Basically, junk in the pipes. Use high-point vents and low-point drains. Use temporary strainers. If the oil isn't clear, don't start the machine.

The "Punch List" is a living document.
A punch list isn't a "to-do" list you make at the end. It should start the day the first piece of steel is erected. Categorize them.

  • Category A items: Must be fixed before commissioning (Safety/Function).
  • Category B items: Can be fixed after startup but before final handover.
    Don't let them bleed together.

Manage your spares.
You will break things during commissioning. You will blow fuses. You will tear gaskets. If you don't have a "commissioning spares" kit on-site, you’ll be waiting three weeks for a $10 part while your $1,000-an-hour consultants sit in their trailers drinking coffee.

Document everything.
In three years, when there is a warranty claim, the first thing the lawyers will ask for is the commissioning report. If you don't have the signed-off loop check sheet or the vibration analysis report from day one, you have no leg to stand on.

Final Reality Check

Commissioning is the "trial by fire." It’s the most stressful part of any project, but it’s also the most rewarding. It’s the moment a silent, cold hunk of metal becomes a productive asset.

Don't rush it. Don't fake the paperwork. Respect the process, or the process will eventually break you.

The goal isn't just to "finish" the project. The goal is a safe, predictable, and profitable handover. Anything less is just expensive construction.

Actionable Next Steps

  1. Audit your current "Ready for Commissioning" (RFC) status. Don't take the contractor's word for it. Walk the site yourself with the P&IDs (Piping and Instrumentation Diagrams) in hand.
  2. Review the Spare Parts list. Ensure you have at least 20% more gaskets and seals than you think you need for the startup phase.
  3. Hold a "Pre-Commissioning Safety Meeting." Ensure everyone knows that "startup" logic is different from "construction" logic. The site is now live. Energy is present. LOTO (Lockout/Tagout) procedures must be strictly enforced.
  4. Verify the Software. If you have a Distributed Control System (DCS), ensure the logic has been "FAT-ed" (Factory Acceptance Tested) before it ever reaches the site. Bringing buggy code to a live site is a recipe for disaster.